Friday, January 18, 2013

EVM (Earned Value Management) Samples

Problem 0:

·         Project is to install 200 windows.

·         Each week of the project cost is same.

·         Team is paid $4000 every week plus $1000 worth of parts.

·         Project is scheduled for 16 weeks.

·         Calculate – BAC (Project budget)?

·         After four weeks installed windows are 40. Ideally it should be 50 windows.

·         Calculate PV & EV?

 

Answer 0:

 

Problem 0:

Project Duration (wks)

16.00

Each Week Cost

5000.00

BAC($)

80000.00

 

 

After 04 Weeks:

 

Planned % Complete - (50/200)

25.00%

Actual % Complete - (40/200)

20.00%

 

 

Planned Value (PV)($)

20000

Earned Value (EV)($)

16000

 

Since the earned value after four weeks is less than planned value,

That means customer is running in loss.

 

 

Problem 1:

·         Project has a total budget of $3,00,000.

·         So far spent $1,75,000.

·         Team has completed 40% of the project work.

·         However team should have completed 50% of the work.

·         Calculate – EV, SV, CV, SPI, CPI ?

 

Answer 1:

 

Problem 1:

BAC

300000.00

Actual Cost

175000.00

Planned % Complete

50.00%

Actual % Complete

40.00%

 

 

Planned Value (PV)

150000

Earned Value (EV)

120000

 

 

SV (EV-PV)

-30000

CV (EV-AC)

-55000.00

 

 

SPI (EV/PV)

0.8

CPI (EV/AC)

0.69

 

Project is behind schedule and over budget.

 

Problem 2:

·         Project has a total budget of $6,50,000.

·         Total hours of project work 7500

·         So far spent $4,00,000.

·         Team has completed 5100 hrs of the total project work.

·         However team should have completed 4500 hrs of the total project work.

·         Calculate – EV, SV, CV, SPI, CPI ?

 

 

Problem 2:

BAC ($)

650000.00

Actual Cost

400000.00

Total Work

7500.00

 

 

Planned Work (Hrs)

4500.00

Planned % Complete

60.00%

 

 

Actual Work (Hrs)

5100.00

Actual % Complete

68.00%

 

 

Planned Value (PV)($)

390000.00

Earned Value (EV)($)

442000.00

 

 

SV (EV-PV) ($)

52000

CV (EV-AC) ($)

434500.00

 

 

SPI (EV/PV)

1.13

CPI (EV/AC)

1.11

 

Project is early and under budget.

 

 

Problem 3:

·         Project has a total budget of $55,000.

·         So far spent $25,000

·         Planned project duration – 4 weeks.

·         At present project has finished third week and team has completed 50% of the work.

·         Calculate – EV, SV, CV, SPI, CPI ?

 

Note: As project has finished third week of a four week project, so planned % complete is 75%.

 

Problem 3:

BAC ($)

55000.00

Actual Cost

25000.00

Total Duration (Wks)

4.00

 

 

Planned % Complete

75.00%

Actual % Complete

50.00%

 

 

Planned Value (PV)($)

41250.00

Earned Value (EV)($)

27500.00

 

 

SV (EV-PV) ($)

-13750

CV (EV-AC) ($)

2500.00

 

 

SPI (EV/PV)

0.67

CPI (EV/AC)

1.10

 

Project is behind schedule but under budget.

 

Problem 4: Part 1

·         Project is scheduled for two years.

·         You have got six different teams working on five major fucntional areas. Some teams are ahead of schedule and other are failing behind schedule.

·         I.e. Some areas are running under cost and some are over cost and that's making very hard to grasp whether the project is under or over budget.

·         It is nine months into the project.

 

·         Project has a total budget of $42,00000.

·         So far spent $16, 50000

·         CPI is 0.875

·         Calculate – EAC, EV, SV, CV, SPI, and CPI?

 

 

Problem 4:

BAC ($)

4200000.00

Actual Cost

1650000.00

CPI (EV/AC)

0.875

 

 

EAC (BAC/CPI)($)

4800000.00

ETC (EAC-AC)($)

3150000.00

 

 

VAC($) (BAC-EAC)

-600000.00

 

Since the VAC is negative, it means that project is over budget by 60k at completion.

 

Problem 4: Part 2

 

·         Now six months later

·         Cost spent – 2625000

·         Work complete – 70%

·         Calculate – New Forecase values?

 

Problem 4: Part 2

BAC ($)

4200000.00

Actual Cost

2625000.00

Actual % Complete

70.00%

Earned Value (EV)($)

2940000.00

 

 

CPI (EV/AC)

1.120

EAC (BAC/CPI)($)

3750000.00

ETC (EAC-AC)($)

1125000.00

 

 

VAC($) (BAC-EAC)

450000.00

 

Since the VAC is positive, it means that project is under budget by 45k at completion.

 

Problem 5:

 

·         Project is about laying fibre optic cable.

·         Cost of the project is $52 per meter to lay 4 km (4000m) cable.

·         Project duration: 08 weeks

·         Equal amount of cable will be laid in each week (Per week 0.5 km)

·         Current week – 05

·         Cable laid – 1800M

·         Calculate – EV, SV, CV, SPI, and CPI?

 

Problem 5:

BAC ($)

208000.00

Total Duration (Wks)

8.00

 

 

After 05 Weeks:

 

Planned % Complete  (2.5 KM / 4.0 KM)

62.50%

Actual % Complete (1.8 KM / 4.0 KM)

45.00%

 

 

Planned Value (PV)($)

130000

Earned Value (EV)($)

93600

 

 

SV (EV-PV) ($)

-36400

SPI (EV/PV)

0.72

 

So the project is behind schedule.

 

 

Thanks & Regards,

▲T/DG

THE DIGITAL GROUP 

Arun Manglick
Project Manager (PMP, CSM, MS-Project)

Digital Group InfoTech Pvt. Ltd.

Pyramid building, Plot No.5

Rajeev Gandhi InfoTech Park, Phase I,

Hinjewadi, Pune - 411057,  India  

Office: +91 20 66532084

Fax: +91 20 66532052

Mobile: +91 9850901262

 

 

 

 

 

 

 

 

 

 

 

No comments:

Post a Comment