RE: Agile Estimation & Team Velocity

Here is an example of Agile Estimation & Team Velocity:

 

Assumption:

 

Resource Count: 8

Sprint - 4 Weeks (20 Days)

Team Velocity: 2000 Points

Per Sprint Per Resource Velocity: 250 Points

Productive Hours (Per Day): 6.5 Hrs

 

Story Sizes:

 

Story Points

Days

Range (In Days)

Low

10

0.5

0.5-1 Day

Low-Medium

20

1.5

1-2 Days

Medium

30

2.5

2-3 Days

High

50

4.5

4-5 Days

 

 

Resource

Sprint Duration
(4 weeks)

Velocity (Points)

Per Resource (Points)
In 4 Weeks Sprint

8

20

2000

250

 

Below demonstrate kind of proper distribution of stories based on their point based estimate and days based estimate totaling to 2000 Points and 20 Days.

Well there is not necessarily directly proportional relation between story points and days.

 

However I tried demonstrating the same to justify Point Based & Days Based Estimation equally.

 

Estimate (In Days)

4.5

2.5

1.5

0.5

Days

Points
(Per Resource)

Hours
(6.5)

Estimate (In Points)

50

30

20

10

Resource 1

2

2

2

5

20

250

127

Resource 2

3

1

1

5

20

250

130

Resource 3

3

1

1

5

20

250

130

Resource 4

3

1

1

5

20

250

130

Resource 5

3

1

1

5

20

250

130

Resource 6

3

1

1

5

20

250

130

Resource 7

3

1

1

5

20

250

130

Resource 8

3

1

1

5

20

250

130

Total Stories

23

9

9

40

81

2000

1037

Total Points

1150

270

180

400

2000

 

 

Hope this helps.

 